Building since 2013 General contractor · Construction manager · Design-builder CareersNewsroomPrequalifyProject map
Energy · Renewable Energy

Clean power, built to interconnect.

Solar plants, battery storage and wind balance-of-plant, delivered from first pile to commercial operation by teams who plan backward from the interconnection date.

What owners need from us.

01

The interconnection date rules

Grid access, offtake agreements and tax credit timing all hang on one energization date. Missing it costs more than any line item in the budget.

02

Scale multiplies small errors

Tens of thousands of piles and tracker rows mean a small layout or torque error repeats across the site. Quality checks have to keep pace with production.

03

Sites are remote and exposed

Long haul routes, limited water, heat, wind and storm water all shape laydown, crew access and the daily plan.

Renewable Energy

What we build.

  1. 01

    Utility-scale solar

    Pile driving, single-axis tracker installation, module setting, DC collection and inverter pads across large arrays.

  2. 02

    Battery energy storage

    Container and enclosure foundations, power conversion equipment, fire protection and medium-voltage tie-ins.

  3. 03

    Wind balance-of-plant

    Access roads, crane pads, turbine foundations and underground collection to the project substation.

  4. 04

    Collector substations and tie lines

    Step-up substations, gen-tie lines and the protection and metering the utility needs to accept power.

How we deliver here.

The capabilities owners in this market rely on most.

Engineer-Procure-Construct (EPC)Deliver

Turnkey EPC from geotechnical work and pile testing through energization and commercial operation.

Civil & InfrastructureBuild

Site grading, access roads, storm water controls and crane pads on large, remote sites.

Supply Chain ManagementPlan

Trackers, modules, inverters and main power transformers tracked from factory to laydown.

SustainabilityPlan

Erosion control, habitat protection and site restoration planned with the permit conditions.

In practice · Utility-Scale Solar Plant

From open range to 200 MW on the grid.

The solar plant was built under an EPC contract. Tracker arrays were installed block by block while the collector substation and a 12-mile tie line were built in parallel, so the plant was ready when the utility granted interconnection.

200 MW
Plant capacity
12
Mile tie line
EPC
Delivery

Questions owners ask us.

How do you keep a large solar site on schedule?

We break the array into blocks with their own pile, tracker, module and electrical crews. Each block is inspected and turned over in sequence, so progress and quality are measured daily.

Do you build the substation and tie line too?

Yes. We build collector substations and gen-tie lines alongside the array and coordinate testing with the utility so the plant can energize on time.

Can you add battery storage to an existing plant?

Yes. We plan storage additions around the operating plant, with foundations, conversion equipment and tie-ins scheduled to limit lost generation.

Renewable Energy

Planning a renewable energy project?

Share the project, the site and the date that matters. A senior builder will come back to you within one business day.