Student Housing · 2023

Student Housing Community

Twenty-two months from contract to keys, with 1,150 beds ready for move-in weekend.

Owner
Confidential
Location
U.S.
Market
Student Housing
Delivery
Design-build
Scale
1,150 beds
Completed
2023
The brief

Student housing delivered in 22 months, ready for move-in weekend.

Student housing has the hardest deadline in building. If the beds are not ready on move-in weekend, students have nowhere to sleep. The project had to go from design to a furnished, inspected building in 22 months, through a long, hot summer that slows every outdoor trade.

How we built it

The approach.

  1. 01

    Repeat the unit, repeat the win

    A small set of standard unit types let crews learn the sequence once and then repeat it floor after floor.

  2. 02

    Bathrooms built off site

    Prefabricated bathroom pods arrived finished and tested, taking the most crowded trade work off the floors.

  3. 03

    Inspections floor by floor

    Each floor was inspected and signed off as it finished, so no single inspection week stood between the team and move-in.

  4. 04

    Ready for the boxes

    Furniture, keys and life-safety tests were complete days ahead, and our team stayed on site through move-in weekend.

The outcome.

1,150Beds
22 moContract to move-in
100%Units furnished before move-in
On dateMove-in weekend

“Move-in weekend comes whether you are ready or not. We made sure every student found a bed and a working shower.”

Superintendent, MarkWester