Student Housing Community
Twenty-two months from contract to keys, with 1,150 beds ready for move-in weekend.
- Owner
- Confidential
- Location
- U.S.
- Market
- Student Housing
- Delivery
- Design-build
- Scale
- 1,150 beds
- Completed
- 2023
Student housing delivered in 22 months, ready for move-in weekend.
Student housing has the hardest deadline in building. If the beds are not ready on move-in weekend, students have nowhere to sleep. The project had to go from design to a furnished, inspected building in 22 months, through a long, hot summer that slows every outdoor trade.
The approach.

- 01
Repeat the unit, repeat the win
A small set of standard unit types let crews learn the sequence once and then repeat it floor after floor.
- 02
Bathrooms built off site
Prefabricated bathroom pods arrived finished and tested, taking the most crowded trade work off the floors.
- 03
Inspections floor by floor
Each floor was inspected and signed off as it finished, so no single inspection week stood between the team and move-in.
- 04
Ready for the boxes
Furniture, keys and life-safety tests were complete days ahead, and our team stayed on site through move-in weekend.
The outcome.
“Move-in weekend comes whether you are ready or not. We made sure every student found a bed and a working shower.”
Superintendent, MarkWester




Planning something like this?
Share the project, the site and the date that matters. A senior builder will come back to you within one business day.